Demo of existing utilities and installation of new water, fire line, and sewer mains for the new football stadium. Bypass pumping of existing 12” sewer main for new 12” main on the side of the road. Multiple demo areas and all installs of new lines around existing utilities and infrastructure.
Approximately 1800 LF of new sewer main and service lines-12”, 8”, 6”, 4”
Approximately 1200 LF of new water and fire lines- 8”, 6”, 4”